PRINCE2 Foundation (Version 7)
Domain 4Objective 21
4.4.2 Describe the Key Relationships Between the ‘quality’ Practice and the Principles (8.7, Tab 8.3) PRINCE2-FOUNDATION-VERSION-7 Practice Questions (Page 3)
Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 30 practice questions to prepare you well beyond it. (estimate)
30questions here
6free pages
8concepts
60%of the exam
Questions 11–15
- 11
A multinational project is being run in a country with strict data protection regulations. The project involves developing a customer data processing system. The organization's standard quality management approach includes a specific quality review process. How should the project manager tailor the quality practice to suit this environment?
Select an answer first - 12
In a project to upgrade a hospital's patient records system, the project manager is defining the quality roles. The project board wants to ensure that quality is independently checked. According to the 'defined roles and responsibilities' principle, what should the project manager do?
Select an answer first - 13
How does the quality practice incorporate lessons learned?
Select an answer first - 14
A project is creating a new online learning platform. The product description for the 'course enrollment' feature specifies that it must handle 1,000 concurrent users without performance degradation. During development, the team delivers a version that handles only 800 concurrent users. What should the project manager do to uphold the 'focus on products' principle?
Select an answer first - 15
In a project to implement a new payroll system, the project manager is defining how quality will be managed. The organization has a quality assurance department that will provide independent checks, and the project team will perform quality control activities. According to the 'defined roles and responsibilities' principle, what should the project manager do to ensure clarity?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.