4.7.1 Explain the Purpose of the ‘progress’ Practice (11.1) PRINCE2-FOUNDATION-VERSION-7 Practice Questions (Page 1)

Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 11 practice questions to prepare you well beyond it. (estimate)

11questions here
3free pages
1concept
60%of the exam

Questions 1–5

  1. 1foundation · easy

    In PRINCE2, which practice is responsible for forecasting the project's continued viability and controlling unacceptable deviations?

    Select an answer first
  2. 2application · medium

    A project manager is using the progress practice to monitor a project. The project is in the initiation stage. The project manager has produced a detailed plan for the first stage and an outline plan for the rest of the project. What is the primary purpose of the progress practice during this stage?

    Select an answer first
  3. 3application · medium

    A project manager is monitoring a project's progress. The project's business case is based on a specific market window. The project manager has received a report indicating that the project is on schedule and within budget. However, a competitor has just launched a similar product, which may reduce the project's expected benefits. What should the project manager do according to the progress practice?

    Select an answer first
  4. 4foundation · easy

    What is the primary purpose of the 'progress' practice in PRINCE2?

    Select an answer first
  5. 5application · medium

    A project is running a stage that is planned to last six months. At the end of the third month, the project manager notices that the actual cost is 15% over budget, but the time variance is within tolerance. The project board has set a cost tolerance of 10% for this stage. What should the project manager do first, according to the progress practice?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PeopleCert. “PRINCE2-FOUNDATION-VERSION-7” is a trademark of its owner, used for identification only.