Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 11 practice questions to prepare you well beyond it. (estimate)
11questions here
3free pages
1concept
60%of the exam
Questions 11–11
- 11
A project manager is reviewing the progress of a project. The project's stage plan shows that the stage should be completed in four months. At the end of the second month, the project manager calculates that the project will be completed in five months if the current trend continues. The project board has set a time tolerance of one month for the stage. What should the project manager do?
Select an answer first
Finished these 1 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PRINCE2-FOUNDATION-VERSION-7
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PeopleCert. “PRINCE2-FOUNDATION-VERSION-7” is a trademark of its owner, used for identification only.