Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 20 practice questions to prepare you well beyond it. (estimate)

20questions here
4free pages
3concepts
60%of the exam

Questions 1–5

  1. 1expert · medium

    A project manager is planning a project to build a new office building. The project manager has created a work breakdown structure (WBS) that includes the following components: design, construction, and handover. The project manager is now preparing the project plan. The project manager needs to ensure that the plan is aligned with the business case. Which of the following is the most important action to take?

    Select an answer first
  2. 2application · medium

    A project is developing a new mobile banking app. The project manager is creating the project plan. The business interest is concerned with the app's profitability, the user interest is concerned with the app's ease of use, and the supplier interest is concerned with the app's technical reliability. The project manager needs to ensure that the plan addresses all three interests. Which action best demonstrates this?

    Select an answer first
  3. 3foundation · easy

    In PRINCE2, which role is accountable for the project's success and is the ultimate decision-maker for the project?

    Select an answer first
  4. 4application · medium

    A project is underway to upgrade the company's network infrastructure. The project manager is responsible for day-to-day management. The project board has delegated the responsibility for monitoring the project's progress against the plan and ensuring that the project remains viable to a specific role. Which role is responsible for this?

    Select an answer first
  5. 5expert · medium

    A project manager is planning a project to upgrade the company's IT infrastructure. The project manager has created a work breakdown structure (WBS) that includes the following components: assessment, design, implementation, and testing. The project manager is now preparing the project plan. The project manager needs to ensure that the plan is realistic and achievable. Which of the following is the most important action to take?

    Select an answer first