4.7.3 Explain the Purpose of the Key Management Products Required to Support the ‘progress’ Practice: (11.5) PRINCE2-FOUNDATION-VERSION-7 Practice Questions (Page 1)
Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 19 practice questions to prepare you well beyond it. (estimate)
19questions here
4free pages
9concepts
60%of the exam
Questions 1–5
- 1
What is the primary purpose of a Checkpoint Report in PRINCE2?
Select an answer first - 2
Which management product includes the digital and data management approach that defines how digital and data assets are managed during the project?
Select an answer first - 3
What is the primary purpose of a Daily Log in PRINCE2?
Select an answer first - 4
Which management product is produced at the end of each stage and is used by the Project Board to decide whether to proceed to the next stage?
Select an answer first - 5
Which management product is used to capture lessons throughout the project for continuous learning?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PeopleCert. “PRINCE2-FOUNDATION-VERSION-7” is a trademark of its owner, used for identification only.