4.7.4 Define Key Concepts Related to the ‘progress’ Practice PRINCE2-FOUNDATION-VERSION-7 Practice Questions (Page 1)
Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 19 practice questions to prepare you well beyond it. (estimate)
19questions here
4free pages
4concepts
60%of the exam
Questions 1–5
- 1
A project manager is managing a construction project. The project board has set a tolerance of ±10% on the project's timeline. The project manager forecasts that the project will finish 12% later than planned. What should the project manager do?
Select an answer first - 2
During a project, the project manager receives a forecast that the project's timeline will exceed the stage tolerance by two weeks. The project board has not yet been informed. What is the first action the project manager should take?
Select an answer first - 3
In PRINCE2, what is an exception?
Select an answer first - 4
What is the purpose of tolerance in PRINCE2?
Select an answer first - 5
In PRINCE2, which statement about tolerance levels is true?
Select an answer first