Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 19 practice questions to prepare you well beyond it. (estimate)

19questions here
4free pages
4concepts
60%of the exam

Questions 11–15

  1. 11application · medium

    A project manager is reviewing the progress of a marketing campaign. The team has completed 60% of the work but has consumed 80% of the budget. The project manager needs to inform the project board about the likely final cost. What should the project manager provide?

    Select an answer first
  2. 12application · medium

    A project board has delegated authority to a project manager to manage a stage within a cost tolerance of ±10%. The project manager forecasts that the stage cost will be 12% over budget. What is the project manager's responsibility?

    Select an answer first
  3. 13expert · medium

    A project manager is managing a stage with a cost tolerance of ±5%. The project manager receives a forecast that the stage will exceed its cost tolerance by 8%. The project board is on leave for two weeks. What should the project manager do?

    Select an answer first
  4. 14expert · medium

    A project manager is managing a project with a cost tolerance of ±5% at the project level. The project board has delegated a stage tolerance of ±10% to the project manager. The project manager forecasts that the stage will exceed its stage tolerance by 12%, but the project-level tolerance will still be met. What should the project manager do?

    Select an answer first
  5. 15application · medium

    A project board has set a tolerance of ±5% on the project's cost. The project manager forecasts that the cost will be 4% over budget. What should the project manager do?

    Select an answer first