Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 19 practice questions to prepare you well beyond it. (estimate)
19questions here
4free pages
4concepts
60%of the exam
Questions 16–19
- 16
A project manager is overseeing a construction project. The project board has requested a monthly progress report and also wants to be notified immediately if any stage tolerance is forecast to be exceeded. Which combination of controls is the project manager applying?
Select an answer first - 17
A project manager is managing a software upgrade. The project board has set a tolerance of ±5% on the project's cost. The project manager forecasts that the final cost will exceed the tolerance by 8%. What should the project manager do?
Select an answer first - 18
In the context of the PRINCE2 progress practice, what is the purpose of a forecast?
Select an answer first - 19
A project manager is managing a stage. The stage's cost tolerance is ±10%. The project manager receives a forecast that the stage will exceed its cost tolerance by 15%. What should the project manager do first?
Select an answer first
Finished these 4 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PRINCE2-FOUNDATION-VERSION-7
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PeopleCert. “PRINCE2-FOUNDATION-VERSION-7” is a trademark of its owner, used for identification only.