4.6.3 Explain the Purpose of the Key Management Products Required to Support the ‘issues’ Practice: (10.5) PRINCE2-FOUNDATION-VERSION-7 Practice Questions (Page 1)

Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 24 practice questions to prepare you well beyond it. (estimate)

24questions here
5free pages
3concepts
60%of the exam

Questions 1–5

  1. 1application · medium

    During a project, a team member raises a concern about a potential delay in a deliverable. The project manager wants to ensure that this concern is not forgotten and is tracked until it is resolved. What should the project manager do?

    Select an answer first
  2. 2application · medium

    A project manager is setting up the project log for a new project. The project manager wants to ensure that all issues raised during the project are captured in one place. What should the project manager do?

    Select an answer first
  3. 3expert · hard

    A project manager is defining the issue management approach for a project with a tight budget. The project manager wants to minimize the cost of managing issues while still ensuring that all issues are captured and resolved. What should the project manager do?

    Select an answer first
  4. 4expert · hard

    A project manager is leading a project with a complex issue management approach that requires all issues to be logged in the issue register and significant issues to have an issue report. A team member raises a concern that could be either a risk or an issue. The project manager needs to decide how to handle it. What should the project manager do first?

    Select an answer first
  5. 5expert · hard

    A project manager is reviewing the issue register and finds that an issue has been open for a long time without progress. The issue is not significant enough to require an issue report, but it is affecting the team's morale. What should the project manager do?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PeopleCert. “PRINCE2-FOUNDATION-VERSION-7” is a trademark of its owner, used for identification only.