Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 28 practice questions to prepare you well beyond it. (estimate)
28questions here
6free pages
8concepts
60%of the exam
Questions 16–20
- 16
A project is at the end of stage 1. The project manager has collected lessons from the team, but the project board is concerned that lessons from previous projects were not applied. What should the project manager do to address this concern?
Select an answer first - 17
A large, complex project with multiple work streams is being planned. The project manager wants to ensure that progress is monitored effectively without overwhelming the project board. Which approach best reflects the tailor to suit the project environment principle?
Select an answer first - 18
A project is delivering a new HR system. At the end of stage 2, the project manager reports that the stage is within tolerance, but the business case shows that the benefits forecast has dropped below the minimum acceptable return. The project board is about to authorize stage 3. What should the project manager do?
Select an answer first - 19
What is the purpose of a stage boundary in the progress practice?
Select an answer first - 20
What is the primary focus of progress checks in the progress practice?
Select an answer first