4.1.1 Explain the Purpose of the ‘business Case’ Practice (5.1) PRINCE2-FOUNDATION-VERSION-7 Practice Questions (Page 4)

Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 24 practice questions to prepare you well beyond it. (estimate)

24questions here
5free pages
4concepts
60%of the exam

Questions 16–20

  1. 16expert · hard

    A project to migrate a company's data center to the cloud is in the delivery stage. The project board has received a report showing that the project is behind schedule and over budget. The project manager has updated the business case, which now shows the project is still viable but with reduced benefits. What should the project board do?

    Select an answer first
  2. 17expert · hard

    A project to upgrade a manufacturing plant's control systems is in the delivery stage. A new regulation has been announced that will require additional safety features, increasing costs by 30%. The project manager has updated the business case, which now shows the project is no longer viable. However, stopping the project would leave the plant non-compliant with the new regulation. What should the project manager do?

    Select an answer first
  3. 18application · medium

    A project board is reviewing a business case that shows the project is desirable (benefits outweigh costs) but not achievable (the required technology is not yet available). According to PRINCE2, what should the project board do?

    Select an answer first
  4. 19foundation · easy

    What is the primary purpose of the business case practice in PRINCE2?

    Select an answer first
  5. 20application · easy

    A project manager is preparing the business case for a new customer relationship management (CRM) system. Which set of elements must the business case include to be complete?

    Select an answer first