Examers.io
ExamsOrganizationsHow it worksPricingHelp & FAQ
PeopleCert logo

PRINCE2 Foundation (Version 7)

Domain 4Objective 2

4.1.1 Explain the Purpose of the ‘business Case’ Practice (5.1) PRINCE2-FOUNDATION-VERSION-7 Practice Questions (Page 2)

Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 24 practice questions to prepare you well beyond it. (estimate)

24questions here
5free pages
4concepts
60%of the exam

Questions 6–10

  1. 6foundation · easy

    Which statement best describes the role of the business case practice in PRINCE2?

    Select an answer first
  2. 7application · easy

    A project manager is preparing the business case for a new project. The project is expected to generate significant benefits, but the costs are also high, and there are several risks that could affect the project's success. What is the primary purpose of the business case in this scenario?

    Select an answer first
  3. 8application · easy

    A project manager is updating the business case for a project that is in the delivery stage. The project's costs have increased, and the expected completion date has been extended by three months. What should the project manager update in the business case?

    Select an answer first
  4. 9application · medium

    A construction company is initiating a new project to build a warehouse. During the initiating a project process, the project manager needs to create an initial version of the business case. What is the primary purpose of this initial version?

    Select an answer first
  5. 10expert · hard

    A project to develop a new product is in the delivery stage. The project board has received a request for a change that would increase the project's costs by 10% but also increase the expected benefits by 15%. The project manager has updated the business case to reflect this change. What should the project board do?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PeopleCert. “PRINCE2-FOUNDATION-VERSION-7” is a trademark of its owner, used for identification only.