Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 35 practice questions to prepare you well beyond it. (estimate)

35questions here
7free pages
9concepts
60%of the exam

Questions 26–30

  1. 26application · medium

    A project manager is initiating a project to develop a new customer relationship management system. The executive board has emphasized that the system must meet strict data privacy regulations. The project manager needs to ensure that all project products, including the system itself and its documentation, are assessed against defined quality criteria. What should the project manager do first to establish how quality will be managed?

    Select an answer first
  2. 27expert · hard

    A project is developing a new medical device. The project board is concerned about regulatory compliance and wants to ensure that the project's quality procedures are appropriate and being followed. The project manager has received a report from the project assurance indicating that some quality procedures are not being followed consistently. What should the project manager do?

    Select an answer first
  3. 28application · medium

    A project is nearing closure. The project manager is preparing the end project report and needs to confirm that all products have met their quality criteria. What should the project manager do to gather this information?

    Select an answer first
  4. 29expert · hard

    A project is nearing the end of a stage. The project manager is preparing the stage report for the project board. The project board has asked for a summary of the quality activities completed in the stage and any issues that arose. The project manager has access to the quality register, the quality management approach, and the lessons log. What should the project manager use to provide the most accurate and comprehensive summary?

    Select an answer first
  5. 30foundation · easy

    What is the purpose of the quality register in PRINCE2?

    Select an answer first