4.3.2 Describe the Key Relationships Between the ‘plans’ Practice and the Principles (7.7, Tab 7.2) PRINCE2-FOUNDATION-VERSION-7 Practice Questions (Page 3)

Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)

27questions here
6free pages
8concepts
60%of the exam

Questions 11–15

  1. 11application · medium

    A government agency is planning a project to digitize its records. The lessons log from a previous digitization project notes that the team struggled because the project plan did not include enough detail on data migration. The project manager is now creating the project plan. How should the project manager apply the 'learn from experience' principle?

    Select an answer first
  2. 12foundation · easy

    Which of the following is the purpose of the plans practice in PRINCE2?

    Select an answer first
  3. 13foundation · easy

    How does the plans practice enable management by exception?

    Select an answer first
  4. 14application · medium

    A retail company is running a project to open a new distribution center. The business case states that the center will reduce delivery times by 20%. The project plan shows the center will be operational in 12 months. During stage 3, a competitor opens a similar center, and the market analysis shows the expected benefit may be reduced. What should the project manager do to support continued business justification?

    Select an answer first
  5. 15expert · hard

    A telecommunications company is running a project to roll out a new 5G network. The project board has set a project-level cost tolerance of ±5% and a stage-level tolerance of ±10% for stage 2. The project manager forecasts that stage 2 will be 8% over its cost tolerance, but the overall project will still be within the project-level tolerance. What should the project manager do?

    Select an answer first