4.7.5 Describe the Guidance for Effective Management of Progress PRINCE2-FOUNDATION-VERSION-7 Practice Questions (Page 5)
Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 25 practice questions to prepare you well beyond it. (estimate)
25questions here
5free pages
7concepts
60%of the exam
Questions 21–25
- 21
A project manager is conducting a review at the end of a stage. The review reveals that a particular vendor's performance was poor, causing delays. What should the project manager do with this information?
Select an answer first - 22
A project manager is planning a new stage. The project board has set a cost tolerance of ±10% and a time tolerance of ±2 weeks. The project manager forecasts that the stage will be completed within the cost tolerance but will exceed the time tolerance by 3 weeks. What should the project manager do?
Select an answer first - 23
What is the primary purpose of reviewing progress against plans in PRINCE2?
Select an answer first - 24
A project manager is monitoring a project that is behind schedule. The project manager uses current progress data to predict the likely completion date. What is this practice called?
Select an answer first - 25
In PRINCE2, who is responsible for setting the project-level tolerances for time and cost?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.