Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 25 practice questions to prepare you well beyond it. (estimate)
25questions here
5free pages
7concepts
60%of the exam
Questions 6–10
- 6
In PRINCE2, which type of control is used to monitor progress at regular intervals?
Select an answer first - 7
A project manager wants to improve the accuracy and timeliness of progress reports. The project uses a project management information system that tracks tasks and milestones. What is the most effective way to use this system?
Select an answer first - 8
A project manager is managing a project with a fixed budget. The project board has set a cost tolerance of ±5%. The project manager forecasts that the project will exceed the cost tolerance by 3% due to unexpected regulatory requirements. What should the project manager do?
Select an answer first - 9
Which report in PRINCE2 provides the project board with a summary of progress against the current stage plan?
Select an answer first - 10
Which of the following is an example of an event-driven control in PRINCE2?
Select an answer first