4.3.4 Define Key Concepts Related to the ‘plans’ Practice PRINCE2-FOUNDATION-VERSION-7 Practice Questions (Page 3)
Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 26 practice questions to prepare you well beyond it. (estimate)
26questions here
6free pages
7concepts
60%of the exam
Questions 11–15
- 11
In PRINCE2, what is the purpose of the project plan?
Select an answer first - 12
A project schedule shows that activity P must finish before activity Q can start. The project manager wants to identify the relationship between P and Q. What is this relationship called?
Select an answer first - 13
Who typically creates a team plan in PRINCE2?
Select an answer first - 14
A project manager needs to communicate the planned dates for key milestones and activities to stakeholders. What should be used?
Select an answer first - 15
A project manager needs to show the timeline of when activities and milestones are planned to occur. What should be created?
Select an answer first