4.2.4 Define Key Concepts Related to the ‘organizing’ Practice PRINCE2-FOUNDATION-VERSION-7 Practice Questions (Page 4)
Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 21 practice questions to prepare you well beyond it. (estimate)
21questions here
5free pages
6concepts
60%of the exam
Questions 16–20
- 16
What is the primary responsibility of team members in a PRINCE2 project?
Select an answer first - 17
A project to upgrade a hospital's patient records system is underway. The project board has approved the initiation stage plan and the project manager is now managing the work. A critical supplier has informed the project manager that a key component will be delayed by three weeks, which will cause the project to exceed its stage cost tolerance. What must the project manager do?
Select an answer first - 18
What is the main difference between project assurance and project support in PRINCE2?
Select an answer first - 19
A project to implement a new inventory management system is in the initiating stage. The project board has approved the project brief and the project manager is now preparing the project plan. The project board has set a cost tolerance of ±5% for the project. During planning, the project manager realizes that the project will likely exceed the cost tolerance by 10%. What should the project manager do?
Select an answer first - 20
A project is being planned to implement a new customer relationship management (CRM) system. The project manager is assigned, and the project board is formed. The project manager will be supported by a project support office. The project manager will also need to coordinate the work of several specialist teams, each with a team manager. Which of the following is NOT a responsibility of the project manager?
Select an answer first