PRINCE2 Foundation (Version 7)
Domain 4Objective 16
4.3.3 Explain the Purpose of the Key Management Products Required to Support the ‘plans’ Practice: (7.5) PRINCE2-FOUNDATION-VERSION-7 Practice Questions (Page 3)
Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 19 practice questions to prepare you well beyond it. (estimate)
19questions here
4free pages
6concepts
60%of the exam
Questions 11–15
- 11
A project board is reviewing the project plan for a new HR system. They notice that the plan includes the major stages, resources, and controls, but does not include the acceptance criteria for the final product. What should the project manager do?
Select an answer first - 12
In PRINCE2, which management product is used to formally delegate responsibility for producing one or more products to a team manager?
Select an answer first - 13
Who approves an exception plan in PRINCE2?
Select an answer first - 14
What is the main purpose of the project product description in PRINCE2?
Select an answer first - 15
A project is being initiated to deliver a new customer relationship management system. The project board has approved the project plan, which shows three management stages. The project manager is now preparing the first stage plan. Which management product should the project manager use to ensure the stage plan includes the acceptance criteria that the final product must meet?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.