4.6.4 Define Key Concepts Related to the ‘issues’ Practice PRINCE2-FOUNDATION-VERSION-7 Practice Questions (Page 2)

Part of the Understand the PRINCE2 practices and how they are applied throughout the project domain, which accounts for 60% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~15–24 in this domain), expect 1–1 from this objective — we provide 18 practice questions to prepare you well beyond it. (estimate)

18questions here
4free pages
4concepts
60%of the exam

Questions 6–10

  1. 6application · medium

    A project is developing a new mobile app. The project plan and the functional specifications have been baselined. During development, a team member realizes that a planned feature cannot be implemented as specified due to a technical limitation. The project manager needs to assess the impact of this issue. What is the primary reference point for this assessment?

    Select an answer first
  2. 7expert · hard

    A project is building a new hospital wing. The project plan and the architectural drawings have been baselined. The project manager receives two pieces of information on the same day: 1) a supplier informs them that a specific type of steel beam is no longer available and a substitute will be provided, and 2) a stakeholder suggests adding a new patient monitoring system that was not in the original scope. The project manager needs to log both. How should these be classified?

    Select an answer first
  3. 8application · medium

    A project is building a new website. The project board has approved the design and it is baselined. A user group now requests a change to the color scheme. The project manager assesses the change and determines it will take 2 extra days and cost $5,000. The project board has delegated authority to the project manager to approve changes up to $10,000. What should the project manager do?

    Select an answer first
  4. 9foundation · easy

    In PRINCE2, which statement best defines an 'issue'?

    Select an answer first
  5. 10foundation · easy

    Which of the following is typically included in a project baseline?

    Select an answer first