Part of the Schedule Monitoring and Controlling domain, which accounts for 35% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~32–54 in this domain), expect 5–9 from this objective — we provide 40 practice questions to prepare you well beyond it. (estimate)
40questions here
8free pages
12concepts
35%of the exam
Questions 36–40
- 36
What should you do if a subcontractor's schedule shows a completion date later than the project's required date?
Select an answer first - 37
What is the total float (slack) of an activity on the critical path?
Select an answer first - 38
A project manager is analyzing the schedule and finds that the critical path has a total float of -5 days. The project is behind schedule, and the project manager needs to recommend a recovery plan. Which option is the most appropriate?
Select an answer first - 39
Which publication provides a widely recognized industry standard for developing and maintaining project schedules?
Select an answer first - 40
A project manager notices that a key resource was reassigned to another project for two weeks, causing a delay in a non-critical activity. The project manager updates the schedule to reflect the new start date. What is the most important next step?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PMI-SP
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-SP” is a trademark of its owner, used for identification only.