Part of the Schedule Closeout domain, which accounts for 6% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~5–9 in this domain), expect 1–2 from this objective — we provide 21 practice questions to prepare you well beyond it. (estimate)
21questions here
5free pages
4concepts
6%of the exam
Questions 1–5
- 1
A project's contract requires the customer to accept the 'final schedule'. The project manager has prepared the final schedule, but the customer is refusing to sign, claiming the schedule shows a project completion date that is 15 days later than the date promised in the project charter. The project manager knows the charter date was an early estimate, and the approved baseline schedule, which the customer signed, had the later date. What is the MOST appropriate action for the project manager?
Select an answer first - 2
What is the first step in the final acceptance process for contractual schedule components?
Select an answer first - 3
How does obtaining final acceptance of schedule components contribute to project closeout?
Select an answer first - 4
During schedule closeout, which document would you reference to determine which schedule components require formal acceptance?
Select an answer first - 5
Which action best represents obtaining formal acceptance of contractual schedule components?
Select an answer first