Task 1 Collect Activity Status at Defined Intervals from Activity Owners via Reports, Meetings, Inspections, or Other Standard Procedures in Order to Update and Review the Project Progress. PMI-SP Practice Questions (Page 1)
Part of the Schedule Monitoring and Controlling domain, which accounts for 35% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~32–54 in this domain), expect 5–9 from this objective — we provide 23 practice questions to prepare you well beyond it. (estimate)
23questions here
5free pages
5concepts
35%of the exam
Questions 1–5
- 1
A project has a high-risk activity that could delay the critical path if it slips. Which status collection interval is most appropriate for this activity?
Select an answer first - 2
A project manager updates the schedule with the latest status and notices that the project's float on a non-critical path has decreased significantly. What is the most appropriate action?
Select an answer first - 3
What is the primary purpose of communicating with activity owners to obtain status updates?
Select an answer first - 4
An activity owner provides a status update that conflicts with the project manager's observations. What is the most appropriate action for the project manager?
Select an answer first - 5
A project manager is defining the status collection intervals for a project that has a fixed completion date and a penalty for late delivery. The project has several activities with high uncertainty. The team is already working overtime. Which interval strategy is most appropriate?
Select an answer first