Task 1 Collect Activity Status at Defined Intervals from Activity Owners via Reports, Meetings, Inspections, or Other Standard Procedures in Order to Update and Review the Project Progress. PMI-SP Practice Questions (Page 5)
Part of the Schedule Monitoring and Controlling domain, which accounts for 35% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~32–54 in this domain), expect 5–9 from this objective — we provide 23 practice questions to prepare you well beyond it. (estimate)
23questions here
5free pages
5concepts
35%of the exam
Questions 21–23
- 21
A project manager updates the project schedule with the latest status and finds that the project's total float has decreased from 10 days to 2 days. The project is not yet on the critical path, but the float is now very low. What is the most appropriate action?
Select an answer first - 22
Which factor most directly determines the appropriate interval for collecting activity status updates from activity owners?
Select an answer first - 23
A project manager notices that the actual progress of a task is consistently behind the planned schedule. What does this indicate?
Select an answer first
Finished these 3 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PMI-SP
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-SP” is a trademark of its owner, used for identification only.