Task 1 Collect Activity Status at Defined Intervals from Activity Owners via Reports, Meetings, Inspections, or Other Standard Procedures in Order to Update and Review the Project Progress. PMI-SP Practice Questions (Page 2)
Part of the Schedule Monitoring and Controlling domain, which accounts for 35% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~32–54 in this domain), expect 5–9 from this objective — we provide 23 practice questions to prepare you well beyond it. (estimate)
23questions here
5free pages
5concepts
35%of the exam
Questions 6–10
- 6
An activity owner is located in a different time zone and has limited availability. The project manager needs to collect status updates without causing frustration. Which communication method is most appropriate?
Select an answer first - 7
A project manager collects status updates from activity owners during a weekly meeting. After the meeting, the project manager updates the project schedule in the tracking system. What is the most important reason to record the status promptly after collection?
Select an answer first - 8
What is the purpose of comparing updated project progress with the planned schedule?
Select an answer first - 9
After updating the project schedule with the latest status, the project manager compares the actual progress to the baseline and finds that the critical path is now two weeks behind. What is the most appropriate immediate action?
Select an answer first - 10
A project manager has collected status updates and updated the schedule. The project is currently 5% behind on the critical path but has a positive schedule variance on a non-critical path. What is the most appropriate interpretation?
Select an answer first