Task 4 Identify Alternative Project Execution Options, Using Tools and Techniques Such as What-If Scenario Analyses, in Order to Optimize the Schedule. PMI-SP Practice Questions (Page 1)

Part of the Schedule Monitoring and Controlling domain, which accounts for 35% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~32–54 in this domain), expect 5–9 from this objective — we provide 18 practice questions to prepare you well beyond it. (estimate)

18questions here
4free pages
4concepts
35%of the exam

Questions 1–5

  1. 1application · medium

    A construction project is 3 weeks behind schedule due to a delay in foundation work. The project manager runs a what-if analysis showing that adding 5 workers to the critical path activities will recover the delay but will increase costs by 12%. The analysis also shows that overlapping the foundation and framing activities will recover the delay with only a 4% cost increase but introduces a moderate rework risk. The sponsor has a tight budget but accepts moderate risk. Which option should the project manager recommend?

    Select an answer first
  2. 2application · medium

    A project is 2 weeks behind schedule. The project manager runs a what-if analysis and finds that crashing the critical path will recover the delay with a 10% cost increase, while fast-tracking will recover the delay with a 5% cost increase but requires more team coordination. The sponsor approves a budget increase of up to 8%. Which option should the project manager select?

    Select an answer first
  3. 3foundation · easy

    Which alternative execution option involves performing normally sequential activities in parallel to shorten the project schedule?

    Select an answer first
  4. 4application · medium

    A software project is running 2 weeks late. The project manager uses what-if analysis to test three options: (1) adding two developers to the coding phase, (2) moving a non-critical testing task to a later date, and (3) reducing the scope of a low-priority feature. The analysis shows that option 1 brings the project back on track but increases cost by 15%, option 2 has no effect on the critical path, and option 3 brings the project back on track with no cost increase. The sponsor prioritizes cost containment. Which option should the project manager select?

    Select an answer first
  5. 5foundation · easy

    Which of the following is an alternative project execution option used to compress the schedule by adding resources to critical path activities?

    Select an answer first