Task 4 Identify Alternative Project Execution Options, Using Tools and Techniques Such as What-If Scenario Analyses, in Order to Optimize the Schedule. PMI-SP Practice Questions (Page 3)

Part of the Schedule Monitoring and Controlling domain, which accounts for 35% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~32–54 in this domain), expect 5–9 from this objective — we provide 18 practice questions to prepare you well beyond it. (estimate)

18questions here
4free pages
4concepts
35%of the exam

Questions 11–15

  1. 11foundation · easy

    A project manager uses what-if scenario analysis to evaluate the impact of fast-tracking two critical path activities. What is the primary output of this analysis?

    Select an answer first
  2. 12application · medium

    A manufacturing project is behind schedule because a critical machine is only available for a limited number of hours per day. The project manager wants to optimize the schedule without adding significant cost. Which alternative execution option should the project manager consider first?

    Select an answer first
  3. 13application · medium

    A project manager wants to evaluate the impact of a potential 2-week delay in a supplier delivery on the project completion date. The project manager has the project schedule and wants to see how this delay would affect the critical path. Which technique should the project manager use?

    Select an answer first
  4. 14foundation · easy

    In schedule management, what-if scenario analysis is used to:

    Select an answer first
  5. 15foundation · easy

    A project manager has run what-if analyses for two schedule optimization options: crashing and fast-tracking. The crashing option reduces the schedule by 10 days but increases cost by 15%. The fast-tracking option reduces the schedule by 8 days with no additional cost but increases rework risk. Which option should the project manager select?

    Select an answer first