PMIScheduling Professional (PMI-SP)
Domain 2Objective 1
Develop Schedule Model PMI-SP Practice Questions (Page 1)
Part of the Schedule Planning and Development domain, which accounts for 31% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~28–48 in this domain), expect 9–16 from this objective — we provide 26 practice questions to prepare you well beyond it. (estimate)
26questions here
6free pages
6concepts
31%of the exam
Questions 1–5
- 1
What is the primary purpose of incorporating calendars into the schedule model?
Select an answer first - 2
A project manager is sequencing activities for a complex project. There is a mandatory dependency between two activities: 'Install foundation' and 'Erect walls'. There is also a discretionary dependency between 'Erect walls' and 'Install roof' that the team prefers to use. The project manager needs to decide which dependencies to include in the schedule model. What is the best approach?
Select an answer first - 3
Which of the following is an example of a constraint that might be applied to an activity in a schedule model?
Select an answer first - 4
A project manager is developing a schedule for a product launch. The marketing team can start creating the launch materials only after the product design is finalized. The design finalization is a milestone. What type of dependency is this?
Select an answer first - 5
During WBS development, which two inputs are specifically highlighted as essential to ensure complete scope coverage?
Select an answer first