Develop Schedule Model PMI-SP Practice Questions (Page 5)
Part of the Schedule Planning and Development domain, which accounts for 31% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~28–48 in this domain), expect 9–16 from this objective — we provide 26 practice questions to prepare you well beyond it. (estimate)
26questions here
6free pages
6concepts
31%of the exam
Questions 21–25
- 21
A project manager is developing a schedule for a project that involves a team in a country with a national holiday during the project. The holiday is a non-working day for the team. How should this be reflected in the schedule model?
Select an answer first - 22
A project manager is developing a schedule for a marketing campaign. The WBS includes a work package for 'Create promotional materials'. The project manager needs to define the activities and milestones for this work package. What is the next step?
Select an answer first - 23
A project manager is developing the WBS for a new IT system. The sponsor wants to ensure that all deliverables are captured, including those from external vendors. What is the best approach?
Select an answer first - 24
What does the three-point estimating technique use to calculate an expected duration?
Select an answer first - 25
A project manager is estimating the duration for a task that involves laying 1,000 meters of cable. Historical data shows that a similar team can lay 100 meters per day. What estimation technique is being used?
Select an answer first