Part of the Schedule Planning and Development domain, which accounts for 31% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~28–48 in this domain), expect 9–16 from this objective — we provide 26 practice questions to prepare you well beyond it. (estimate)
26questions here
6free pages
6concepts
31%of the exam
Questions 26–26
- 26
A project manager is sequencing activities for a software project. The coding activity can start before the design is fully complete, but the design must be complete before testing can start. What type of dependency is between coding and design?
Select an answer first
Finished these 1 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PMI-SP
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-SP” is a trademark of its owner, used for identification only.