Part of the Schedule Planning and Development domain, which accounts for 31% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~28–48 in this domain), expect 9–16 from this objective — we provide 26 practice questions to prepare you well beyond it. (estimate)

26questions here
6free pages
6concepts
31%of the exam

Questions 11–15

  1. 11application · medium

    A global project has team members in different time zones. The project manager is developing the schedule model and needs to account for the fact that team members in different regions have different working hours and holidays. What should the project manager do?

    Select an answer first
  2. 12application · medium

    A software development project has a WBS with 20 work packages. The project manager needs to assign each work package to a specific team and track performance at a higher level. The organization uses a matrix structure where developers report to both functional and project managers. What is the most effective way to assign responsibility?

    Select an answer first
  3. 13application · medium

    A project manager is sequencing activities for a construction project. The foundation must be completed before the framing can start. The framing cannot start until the building permit is approved by the city. The permit approval is outside the project team's control. What type of dependency is the permit approval?

    Select an answer first
  4. 14application · medium

    A project manager is setting up control accounts for a project. The WBS has 15 work packages, and the OBS has 5 departments. Each work package is assigned to one department. How many control accounts should be established?

    Select an answer first
  5. 15foundation · easy

    In the context of schedule planning, what is the purpose of establishing control accounts?

    Select an answer first