PMIScheduling Professional (PMI-SP)

Domain 5Objective 1

Task 1 Develop and Foster Relationships with Project Stakeholders, Consistent with the Communication Management Plan, in Order to Enhance Support for the Project Schedule. PMI-SP Practice Questions (Page 1)

Part of the Stakeholder Communications Management domain, which accounts for 14% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~13–22 in this domain), expect 3–6 from this objective — we provide 33 practice questions to prepare you well beyond it. (estimate)

33questions here
7free pages
8concepts
14%of the exam

Questions 1–5

  1. 1application · medium

    A project manager has identified a stakeholder who has low influence but high interest in the project schedule. The stakeholder is a subject matter expert whose input is needed for accurate task durations. The communication management plan specifies monthly updates for this stakeholder. What engagement strategy should the project manager use?

    Select an answer first
  2. 2application · medium

    A project manager is halfway through a 12-month construction project. A new regulatory requirement has emerged that will add a month to the schedule. The project manager has an updated stakeholder register and a communication plan that specifies monthly updates. What should the project manager do to sustain stakeholder support during this change?

    Select an answer first
  3. 3expert · hard

    A project manager is managing a long-term project. A stakeholder who was initially classified as having low influence and low interest has recently been promoted to a senior leadership position, giving them high influence over resource allocation. The project manager has not updated the stakeholder register since project initiation. What should the project manager do to maintain support for the schedule?

    Select an answer first
  4. 4application · medium

    A project manager is working with a stakeholder who has high influence and high interest in the schedule. The communication management plan specifies weekly email updates and monthly status meetings for this stakeholder. The stakeholder requests daily phone calls to discuss schedule progress. What should the project manager do?

    Select an answer first
  5. 5application · medium

    During a schedule review, the quality assurance manager insists that a two-week testing phase must be extended by five days, while the sponsor demands the project finish on the original date to meet a regulatory deadline. The communication management plan requires that schedule changes be agreed upon by both parties. What should the project manager do to resolve this conflict and maintain support for the schedule?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.