Part of the Stakeholder Communications Management domain, which accounts for 14% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~13–22 in this domain), expect 3–6 from this objective — we provide 33 practice questions to prepare you well beyond it. (estimate)

33questions here
7free pages
8concepts
14%of the exam

Questions 21–25

  1. 21expert · hard

    A project manager is leading a large infrastructure project with multiple stakeholder groups. The sponsor has high influence and high interest, the end users have low influence and high interest, and a government regulator has high influence but low interest. The project is facing a potential schedule delay due to a permitting issue. The communication management plan specifies different engagement levels for each group. What is the most effective approach to maintain support for the schedule?

    Select an answer first
  2. 22application · medium

    A project manager is facilitating a meeting between the engineering team and the marketing team. The engineering team wants to delay a product launch by two weeks to fix a critical bug, while marketing insists on the original date due to a major advertising campaign. The communication management plan requires that schedule conflicts be resolved collaboratively. What should the project manager do?

    Select an answer first
  3. 23foundation · easy

    What is the primary purpose of soliciting feedback from stakeholders regarding the project schedule?

    Select an answer first
  4. 24application · medium

    A project manager notices that the manufacturing lead has been silent during the last two schedule review meetings and has not responded to emails about a critical milestone. The communication management plan calls for biweekly one-on-one check-ins with key stakeholders. What should the project manager do to maintain trust and support for the schedule?

    Select an answer first
  5. 25application · medium

    A project manager is developing the communication management plan for a new project. The stakeholder analysis shows that the regulatory body has high influence but low interest, and the project team has high interest but low influence. What should the project manager include in the communication plan?

    Select an answer first