Task 6 Update the Schedule Model and Document Schedule Baseline Changes, Received Through Formal Change-Control Processes, in Order to Maintain an Accurate Schedule and Facilitate Forensic Schedule Analysis, If Required. PMI-SP Practice Questions (Page 1)
Part of the Schedule Monitoring and Controlling domain, which accounts for 35% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~32–54 in this domain), expect 5–9 from this objective — we provide 16 practice questions to prepare you well beyond it. (estimate)
16questions here
4free pages
4concepts
35%of the exam
Questions 1–5
- 1
A project is in a dispute with a client over schedule delays. The client claims that the project team caused the delays by not following the approved schedule. The project manager needs to defend the project team's performance. What is the most important evidence to support the defense?
Select an answer first - 2
A project has an approved change that adds two weeks to a task on the critical path. The project scheduler needs to update the schedule model. What is the most appropriate action to maintain data integrity and consistency?
Select an answer first - 3
What is the primary purpose of documenting the outcome of a schedule change request in the formal change-control process?
Select an answer first - 4
A project manager is facing pressure from the sponsor to accelerate the schedule. The sponsor suggests making a schedule change directly without going through the formal change-control process, arguing that the change is necessary to meet the deadline. The project manager knows that the change will affect the baseline. What should the project manager do?
Select an answer first - 5
A project manager receives an urgent request from a stakeholder to add a new deliverable to the project. The stakeholder argues that the change is minor and should be implemented immediately to avoid delaying the next release. The project manager knows that the change will affect the critical path and requires a baseline update. What should the project manager do first?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.