Task 2 Collect Resource Information and Updates via Reports, Timesheets, Meetings, Inspections, or Other Standard Procedures in Order to Report on Resource Utilization and Availability. PMI-SP Practice Questions (Page 1)

Part of the Schedule Monitoring and Controlling domain, which accounts for 35% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~32–54 in this domain), expect 5–9 from this objective — we provide 21 practice questions to prepare you well beyond it. (estimate)

21questions here
5free pages
5concepts
35%of the exam

Questions 1–5

  1. 1foundation · easy

    A team member informs the scheduler that they will be unavailable for two weeks due to a planned medical leave. How should the scheduler update the project schedule to reflect this resource availability change?

    Select an answer first
  2. 2expert · medium

    A project scheduler needs to collect resource availability for the next quarter. The project has a mix of full-time employees, part-time contractors, and resources shared with other projects. What is the most effective method for collecting this information?

    Select an answer first
  3. 3expert · medium

    A project has two critical resources: a senior architect (40 hrs/week) and a junior developer (40 hrs/week). The architect is 100% allocated to the project, and the developer is 80% allocated. The project sponsor asks for a report on whether the team can handle an additional 10 hours of work per week. What is the most accurate response based on the data?

    Select an answer first
  4. 4foundation · easy

    A project scheduler needs to collect information about the availability of a specialized equipment resource. Which standard procedure is most appropriate for this purpose?

    Select an answer first
  5. 5expert · medium

    A project scheduler is updating the schedule for the next month. A key resource has submitted a request for 2 weeks of vacation, but the request is pending approval. The schedule has a critical task assigned to this resource during that period. What is the most appropriate action for the scheduler?

    Select an answer first