PMIScheduling Professional (PMI-SP)
Domain 3Objective 2
Task 2 Collect Resource Information and Updates via Reports, Timesheets, Meetings, Inspections, or Other Standard Procedures in Order to Report on Resource Utilization and Availability. PMI-SP Practice Questions (Page 2)
Part of the Schedule Monitoring and Controlling domain, which accounts for 35% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~32–54 in this domain), expect 5–9 from this objective — we provide 21 practice questions to prepare you well beyond it. (estimate)
21questions here
5free pages
5concepts
35%of the exam
Questions 6–10
- 6
A project sponsor asks for a summary of resource utilization for the past month. The sponsor is not interested in detailed timesheet data but wants to know if the team is over- or under-allocated. What is the most appropriate format for this communication?
Select an answer first - 7
Which of the following is a standard procedure for collecting resource information in a project?
Select an answer first - 8
What is the primary purpose of communicating resource utilization and availability findings to stakeholders?
Select an answer first - 9
A project sponsor needs to know if the project has enough resources to complete the remaining work on schedule. The scheduler has collected utilization data showing the team is at 95% utilization. What is the most important additional information to include in the report to the sponsor?
Select an answer first - 10
A project sponsor requests a resource utilization report. The scheduler has data showing that the team is at 110% utilization, meaning some resources are over-allocated. The sponsor is concerned about the impact on the schedule. What is the most effective way to communicate this information?
Select an answer first