Part of the Schedule Monitoring and Controlling domain, which accounts for 35% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~32–54 in this domain), expect 5–9 from this objective — we provide 21 practice questions to prepare you well beyond it. (estimate)

21questions here
5free pages
5concepts
35%of the exam

Questions 21–21

  1. 21application · medium

    A project scheduler notices that the timesheet system shows a senior engineer at 120% allocation for the week, but the engineer's calendar shows a 3-day training course. The engineer's manager confirms the training was approved. The scheduler must update the resource utilization report. What should the scheduler do first?

    Select an answer first
Finished these 1 questions?

Review the revealed explanations, or continue through the curriculum.

No more pagesBack to PMI-SP

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-SP” is a trademark of its owner, used for identification only.