PMIScheduling Professional (PMI-SP)

Domain 4Objective 3

Task 3 Update the Organizational Process Assets, Through Documentation of Identified Lessons Learned and Best Practices, in Order to Improve Business Processes. PMI-SP Practice Questions (Page 1)

Part of the Schedule Closeout domain, which accounts for 6% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~5–9 in this domain), expect 1–2 from this objective — we provide 13 practice questions to prepare you well beyond it. (estimate)

13questions here
3free pages
4concepts
6%of the exam

Questions 1–5

  1. 1application · medium

    A project manager is closing a project where the schedule was frequently updated without proper change control, causing confusion about the critical path. The organization's scheduling procedure does not address change control for schedule updates. What should the project manager do to improve business processes?

    Select an answer first
  2. 2foundation · easy

    After the project schedule is closed, the project manager updates the organization's lessons learned repository with findings from the schedule. What is this action called?

    Select an answer first
  3. 3application · medium

    A project manager notices that the team's practice of using a 'schedule risk register' that is reviewed weekly helped identify potential delays early. The organization's scheduling methodology does not mention this practice. What should the project manager do?

    Select an answer first
  4. 4application · medium

    During schedule closeout, a project manager notices that the team's practice of holding a 15-minute daily 'schedule health check' caught potential slippage early and kept the project on track. The organization does not currently have this practice documented. What should the project manager do?

    Select an answer first
  5. 5application · medium

    A project manager is conducting a lessons learned session for a schedule that was delayed by a vendor's late delivery of critical equipment. The team identifies that the vendor's lead time was underestimated. What should the project manager do to improve future projects?

    Select an answer first