Task 3 Update the Organizational Process Assets, Through Documentation of Identified Lessons Learned and Best Practices, in Order to Improve Business Processes. PMI-SP Practice Questions (Page 3)

Part of the Schedule Closeout domain, which accounts for 6% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~5–9 in this domain), expect 1–2 from this objective — we provide 13 practice questions to prepare you well beyond it. (estimate)

13questions here
3free pages
4concepts
6%of the exam

Questions 11–13

  1. 11foundation · easy

    During schedule closeout, the team identifies a technique that consistently produced accurate duration estimates. What should be done with this technique to benefit future projects?

    Select an answer first
  2. 12foundation · easy

    A company updates its scheduling procedures to include a new technique that was successful on a recent project. This is an example of:

    Select an answer first
  3. 13foundation · easy

    Which of the following is an example of updating an organizational process asset during schedule closeout?

    Select an answer first
Finished these 3 questions?

Review the revealed explanations, or continue through the curriculum.