Part of the Schedule Closeout domain, which accounts for 6% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~5–9 in this domain), expect 1–2 from this objective — we provide 13 practice questions to prepare you well beyond it. (estimate)
13questions here
3free pages
4concepts
6%of the exam
Questions 11–13
- 11
During schedule closeout, the team identifies a technique that consistently produced accurate duration estimates. What should be done with this technique to benefit future projects?
Select an answer first - 12
A company updates its scheduling procedures to include a new technique that was successful on a recent project. This is an example of:
Select an answer first - 13
Which of the following is an example of updating an organizational process asset during schedule closeout?
Select an answer first
Finished these 3 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PMI-SP
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-SP” is a trademark of its owner, used for identification only.