Examers.io
ExamsOrganizationsHow it worksPricingHelp & FAQ
PMI logo

PMIScheduling Professional (PMI-SP)

Domain 4Objective 4

Task 4 Distribute Final Schedule Reports, Including Earned Value Management (EVM) Calculations and Variance Analysis, to Stakeholders in Order to Facilitate Project Closeout. PMI-SP Practice Questions (Page 1)

Part of the Schedule Closeout domain, which accounts for 6% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~5–9 in this domain), expect 1–2 from this objective — we provide 15 practice questions to prepare you well beyond it. (estimate)

15questions here
3free pages
5concepts
6%of the exam

Questions 1–5

  1. 1expert · hard

    A project manager must distribute the final schedule report to stakeholders, but some stakeholders are external and have limited access to the company's internal project management system. The report contains sensitive cost data. What is the best distribution method?

    Select an answer first
  2. 2foundation · easy

    How does the final schedule report support the lessons learned process during project closeout?

    Select an answer first
  3. 3foundation · easy

    Given PV = $50,000, EV = $45,000, and AC = $40,000, what is the Cost Performance Index (CPI)?

    Select an answer first
  4. 4application · medium

    A project manager is preparing the final schedule report for a software development project. The report will be used to support the formal closure meeting. Which element is most important to include to facilitate the lessons-learned discussion?

    Select an answer first
  5. 5foundation · easy

    Which stakeholder group would most likely require a high-level summary of the final schedule report rather than detailed EVM calculations?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-SP” is a trademark of its owner, used for identification only.