Part of the Schedule Closeout domain, which accounts for 6% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~5–9 in this domain), expect 1–2 from this objective — we provide 15 practice questions to prepare you well beyond it. (estimate)

15questions here
3free pages
5concepts
6%of the exam

Questions 6–10

  1. 6application · medium

    A project manager is creating the final schedule report for a construction project. The report will be shared with the client and the internal management team. Which component is essential to include to show the project's overall schedule performance?

    Select an answer first
  2. 7application · medium

    A project manager is compiling the final schedule report for a marketing campaign project. Which combination of data is essential to include in the report?

    Select an answer first
  3. 8foundation · easy

    Which of the following is a standard component of a final schedule report?

    Select an answer first
  4. 9application · medium

    A project manager is finalizing the schedule report for a project that ended successfully. The report will be used in the closure meeting. What is the primary purpose of including a variance analysis in this report?

    Select an answer first
  5. 10application · medium

    A project manager is preparing the final schedule report for a project that experienced a major delay due to a vendor issue. The report will be used in the closure meeting. What is the best way to present the delay in the report to facilitate lessons learned?

    Select an answer first