Task 1 Obtain Final Acceptance of the Contractual Schedule Components, by Working with Sponsor And/or Customer, in Order to Facilitate Project Closeout. PMI-SP Practice Questions (Page 3)
Part of the Schedule Closeout domain, which accounts for 6% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~5–9 in this domain), expect 1–2 from this objective — we provide 21 practice questions to prepare you well beyond it. (estimate)
21questions here
5free pages
4concepts
6%of the exam
Questions 11–15
- 11
A project manager is seeking final acceptance of the schedule. The customer's authorized signatory is on an extended leave of absence, and no one else has been formally delegated to sign. The project is complete, and the team is waiting for final acceptance to be released from their obligations. What is the BEST course of action to facilitate closeout?
Select an answer first - 12
A project is complete, and the project manager is preparing the final acceptance package. The customer's project manager has verbally confirmed the schedule is acceptable but is refusing to sign the formal acceptance document, stating they are 'too busy' and that a verbal confirmation should be enough. The contract explicitly requires a signed acceptance form. What is the MOST effective strategy to secure the formal signature?
Select an answer first - 13
The contract for a project requires the customer to accept the 'final schedule submission'. The project manager has provided the final schedule, but the customer's representative says they cannot sign it because they need to compare it against the original baseline to verify the project finished on time. The baseline was approved at the start of the project. What should the project manager do?
Select an answer first - 14
A project manager has obtained the customer's signature on the final schedule acceptance form. However, during the final project review, the project manager discovers that a minor schedule update from six months ago was never formally included in the final acceptance package, although it was included in the monthly report. The customer has already signed. What is the MOST appropriate action?
Select an answer first - 15
When coordinating with the customer to secure final acceptance, what should you do if the customer identifies a discrepancy in a schedule report?
Select an answer first