PMIScheduling Professional (PMI-SP)
Domain 4Objective 1
Task 1 Obtain Final Acceptance of the Contractual Schedule Components, by Working with Sponsor And/or Customer, in Order to Facilitate Project Closeout. PMI-SP Practice Questions (Page 4)
Part of the Schedule Closeout domain, which accounts for 6% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~5–9 in this domain), expect 1–2 from this objective — we provide 21 practice questions to prepare you well beyond it. (estimate)
21questions here
5free pages
4concepts
6%of the exam
Questions 16–20
- 16
The project sponsor has signed the final schedule acceptance form. The customer has not yet signed. The project manager is ready to start the final financial closeout activities. What is the MOST appropriate action regarding the customer's pending acceptance?
Select an answer first - 17
A construction project's contract specifies that the contractor must submit monthly schedule updates and a final as-built schedule. The project is complete, and the contractor has submitted the final as-built schedule. The sponsor, however, has not yet signed the acceptance form, stating they want to review the monthly updates from the last three months one more time. The project manager has all the monthly updates archived. What should the project manager do FIRST?
Select an answer first - 18
A project manager is in the final acceptance phase. The customer has signed off on the final schedule, but the project sponsor has not. The sponsor is concerned that the schedule does not reflect the actual resource hours spent. The project manager knows the schedule is accurate and the resource hours are tracked separately in the time management system. What is the BEST way to address the sponsor's concern?
Select an answer first - 19
A project is complete, and the project manager is preparing the final schedule acceptance package. The customer has a new project manager who was not involved in the project and is unfamiliar with the schedule's history. What is the BEST way for the project manager to communicate the schedule information to this new stakeholder?
Select an answer first - 20
Which of the following is typically considered a contractual schedule component that requires final acceptance during project closeout?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.