Part of the Schedule Monitoring and Controlling domain, which accounts for 35% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~32–54 in this domain), expect 5–9 from this objective — we provide 40 practice questions to prepare you well beyond it. (estimate)
40questions here
8free pages
12concepts
35%of the exam
Questions 11–15
- 11
Which of the following is a key element of an effective schedule status report?
Select an answer first - 12
A project manager is comparing planned versus actual progress for a task that was supposed to be 50% complete by the status date. The actual progress is 40%. The task has a total float of one week. What is the most appropriate conclusion?
Select an answer first - 13
What is the purpose of schedule risk and impact analysis?
Select an answer first - 14
What is a best practice for ongoing schedule monitoring?
Select an answer first - 15
A general contractor is reviewing a subcontractor's schedule for a critical foundation pour. The subcontractor's schedule shows the pour completing two weeks later than the project master schedule requires. The subcontractor claims the delay is due to a late equipment delivery that was not their fault. The project manager needs to assess the impact and report to the owner. What should the project manager do first?
Select an answer first