Examers.io
ExamsOrganizationsHow it worksPricingHelp & FAQ
PMI logo

PMIScheduling Professional (PMI-SP)

Domain 3Objective 3

Task 3 Perform Schedule Analysis and Audit, on In-House and Subcontractor Schedules, Using Industry Standards, Guidelines and Best Practices in Order to Identify and Report Project Schedule, Status, Changes, Impacts or Issues. PMI-SP Practice Questions (Page 6)

Part of the Schedule Monitoring and Controlling domain, which accounts for 35% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~32–54 in this domain), expect 5–9 from this objective — we provide 40 practice questions to prepare you well beyond it. (estimate)

40questions here
8free pages
12concepts
35%of the exam

Questions 26–30

  1. 26application · medium

    A project manager is conducting a schedule audit and wants to ensure the schedule complies with industry best practices. Which action best aligns with PMI's Practice Standard for Scheduling?

    Select an answer first
  2. 27foundation · easy

    Why is it important to apply industry standards and guidelines when performing schedule analysis?

    Select an answer first
  3. 28expert · hard

    A project manager needs to report schedule status to a steering committee. The project has an SPI of 0.92 and a critical path delay of three weeks. The project manager has identified that the delay is due to a vendor's late delivery, and a change request has been submitted. What is the most effective way to report this?

    Select an answer first
  4. 29foundation · easy

    Which of the following is an input to assessing the current status of a project schedule?

    Select an answer first
  5. 30foundation · easy

    What is the first step in managing a schedule change?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-SP” is a trademark of its owner, used for identification only.