Task 3 Perform Schedule Analysis and Audit, on In-House and Subcontractor Schedules, Using Industry Standards, Guidelines and Best Practices in Order to Identify and Report Project Schedule, Status, Changes, Impacts or Issues. PMI-SP Practice Questions (Page 7)
Part of the Schedule Monitoring and Controlling domain, which accounts for 35% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~32–54 in this domain), expect 5–9 from this objective — we provide 40 practice questions to prepare you well beyond it. (estimate)
40questions here
8free pages
12concepts
35%of the exam
Questions 31–35
- 31
Which of the following is an example of a schedule risk?
Select an answer first - 32
A subcontractor's schedule shows a critical activity finishing three weeks later than the master schedule. The subcontractor claims that the delay is due to a change in the project scope that was approved by the owner. The project manager has not yet updated the master schedule. What is the most appropriate action?
Select an answer first - 33
A project manager discovers that a team member has been recording progress on a task as 50% complete for three consecutive weeks, even though the task is actually finished. The project manager needs to correct the schedule. What is the most important consideration?
Select an answer first - 34
What does a Schedule Variance (SV) of zero indicate?
Select an answer first - 35
Why is it important to document the cause of a schedule change?
Select an answer first