PMIScheduling Professional (PMI-SP)
Domain 3Objective 3
Task 3 Perform Schedule Analysis and Audit, on In-House and Subcontractor Schedules, Using Industry Standards, Guidelines and Best Practices in Order to Identify and Report Project Schedule, Status, Changes, Impacts or Issues. PMI-SP Practice Questions (Page 2)
Part of the Schedule Monitoring and Controlling domain, which accounts for 35% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~32–54 in this domain), expect 5–9 from this objective — we provide 40 practice questions to prepare you well beyond it. (estimate)
40questions here
8free pages
12concepts
35%of the exam
Questions 6–10
- 6
What does a Schedule Performance Index (SPI) of 0.85 indicate?
Select an answer first - 7
Which of the following is a best practice for schedule control?
Select an answer first - 8
A project manager is evaluating the impact of a potential two-week delay in a non-critical activity that has four weeks of total float. The delay is caused by a supplier issue that is likely to recur. What is the most appropriate action?
Select an answer first - 9
A project has an SPI of 1.05, but the critical path is two weeks behind schedule. The project manager must report to stakeholders. What is the most accurate interpretation?
Select an answer first - 10
During a weekly schedule review, a project manager notices that the actual progress of a task is consistently less than planned, but the SPI is still above 1.0. What is the most likely explanation?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.