PMIScheduling Professional (PMI-SP)
Domain 3Objective 5
Task 5 Incorporate Approved Risk Mitigation Activities into the Schedule, by Utilizing Defined Change Control Processes, in Order to Establish a New Performance Measurement Baseline (PMB). PMI-SP Practice Questions (Page 4)
Part of the Schedule Monitoring and Controlling domain, which accounts for 35% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~32–54 in this domain), expect 5–9 from this objective — we provide 17 practice questions to prepare you well beyond it. (estimate)
17questions here
4free pages
5concepts
35%of the exam
Questions 16–17
- 16
When adding an approved risk mitigation activity to the project schedule, what is the correct sequence of actions?
Select an answer first - 17
A project is behind schedule. The CCB has approved a change to add overtime work as a risk mitigation activity to accelerate the schedule. The project manager has updated the schedule with the overtime activity. What is the NEXT step in the change control process?
Select an answer first
Finished these 2 questions?
Review the revealed explanations, or continue through the curriculum.