Part of the Schedule Monitoring and Controlling domain, which accounts for 35% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~32–54 in this domain), expect 5–9 from this objective — we provide 17 practice questions to prepare you well beyond it. (estimate)

17questions here
4free pages
5concepts
35%of the exam

Questions 6–10

  1. 6foundation · easy

    Which of the following is included in a performance measurement baseline (PMB)?

    Select an answer first
  2. 7foundation · easy

    What is the purpose of a defined change control process when incorporating changes into the project schedule?

    Select an answer first
  3. 8application · medium

    A project manager has received CCB approval to add a risk mitigation activity to the schedule. The activity will be performed by an external vendor and will add two weeks to the project. The project manager updates the schedule and the PMB. What is the PRIMARY purpose of updating the PMB in this situation?

    Select an answer first
  4. 9foundation · easy

    When should the performance measurement baseline (PMB) be updated?

    Select an answer first
  5. 10application · medium

    A project has an approved PMB. The CCB approves a change that adds a risk mitigation activity, which increases the project's total float on the critical path. The project manager updates the schedule. What is the impact on the PMB?

    Select an answer first