Task 5 Incorporate Approved Risk Mitigation Activities into the Schedule, by Utilizing Defined Change Control Processes, in Order to Establish a New Performance Measurement Baseline (PMB). PMI-SP Practice Questions (Page 3)

Part of the Schedule Monitoring and Controlling domain, which accounts for 35% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~32–54 in this domain), expect 5–9 from this objective — we provide 17 practice questions to prepare you well beyond it. (estimate)

17questions here
4free pages
5concepts
35%of the exam

Questions 11–15

  1. 11foundation · easy

    What is the primary purpose of incorporating approved risk mitigation activities into the project schedule?

    Select an answer first
  2. 12foundation · easy

    Which of the following is a typical component of a defined change control process?

    Select an answer first
  3. 13application · medium

    A project manager is reviewing the risk register and identifies several approved risk mitigation activities that have not yet been added to the project schedule. The activities were approved by the CCB as part of a previous change request. What should the project manager do to incorporate these activities into the schedule?

    Select an answer first
  4. 14application · medium

    A project's PMB was approved three months ago. The CCB has just approved a change that adds a quality inspection activity, extending the project duration by five days. The project manager has updated the project schedule. What is the correct action regarding the performance measurement baseline?

    Select an answer first
  5. 15application · medium

    During execution of a software development project, the team identifies a new security risk that requires adding a penetration testing activity to the schedule. The project manager prepares a change request. According to the project's defined change control process, what is the FIRST step the project manager should take before the change can be incorporated into the schedule?

    Select an answer first